Work has already begun on a £200m upgrade of Milton Keynes Central
station to provide more platforms for inter-city trains, allow the
extension of the Bedford-Bletchley branch line route, and provide
capacity for passenger services from Oxford and Aylesbury.

The early stages of the two-year programme began on 4 December
2006 and were completed 2007.
The overall project will include a third northbound fast line and
platform, which will enable consecutive trains to call at Milton Keynes
during peak times.
The total modernisation is scheduled for completion in 2009, enabling more trains to serve more destinations.